In-progress projects

  In-progress orders (in phase of delivery or erection - not commissioned yet) status to 2010-04     
2010 Furnace for heat stabilisation of the shafts to the weight of 60t including equipment for measurement and evaluation of the shaft radial run-out during stabilisation / project, complete delivery including erection and commissioning; 60t electricity I
2010 Furnace for heat stabilisation of the shafts to the weight of 60t including equipment for measurement and evaluation of the shaft radial run-out during stabilisation / project, complete delivery including erection and commissioning; 60t electricity I
2010 Furnace for heat stabilisation of the shafts to the weight of 130t including equipment for measurement and evaluation of the shaft radial run-out during stabilisation / project, complete delivery including erection and commissioning; 130t electricity CZ
2010 Walking-beam furnace 12.5x18m for heating the continuously cast billets before rolling / project of furnace parts, completion, erection, commissioning; 80t/hr gas SK